Project detail
Waverly Dorm
SU_WAVERLY
Projected finish
2027-08-16
Movement Vs Prior Trusted Run
0 days
Delta-sensitive comparison is authoritative against 2026-03-28T21-09-05Z.
Primary Issue / Driver
Top schedule driver 34992 - Frame Walls & Set Door Frames: high_logic_density; high_successor_count; high_predecessor_count; constrained.
Waverly Dorm is critical at a score of 13.0. Schedule logic still contains 2 cycle(s).
Required Action
Scheduler: Validate and remove 2 schedule cycle(s) before the next publish.
Timing: before next publish
Finish Authority
trusted comparison
Published milestone drift log
Derived from the published milestone drift log using the latest milestone finish 2027-08-16 (Project Substantial Completion, activity 142).
Trust / Baseline State
Authoritative delta-driven ranking
Comparison Detail
2026-03-28T21-09-05Z
Delta-sensitive comparison is authoritative against 2026-03-28T21-09-05Z.
Latest Generated Dossier Preview
---
title: Waverly Dorm - Dossier
type: project_dossier
project_code: SU_WAVERLY
project_id: SU_WAVERLY
project_name: Waverly Dorm
health_tier: critical
health_score: 13.0
risk_level: HIGH
generated_at: '2026-03-28T23:29:15Z'
run_date: '2026-03-28'
tags:
- controltower
- project-dossier
- su_waverly
---
# Waverly Dorm
[[Portfolio Weekly Summary]] | [[Weekly Brief]] | [[Weekly/2026-03-21/Projects/SU_WAVERLY/Waverly Dorm - Dossier|Prior Week]]
## Executive Summary
Waverly Dorm is critical at a score of 13.0. Schedule logic still contains 2 cycle(s).
- Project ID: **SU_WAVERLY**
## Current Health
- Tier: **Critical**
- Score: **13.0**
- Risk Level: **HIGH**
- Trust: **Partial**
### Why It Lands Here
- Schedule logic still contains 2 cycle(s).
- Schedule has 131 open-end conditions across starts and finishes.
- Parser warnings are elevated at 2284.
- Margin is under pressure at 5.9%.
- Forecast final cost increased by $206,265.
- Projected profit declined by $190,454 versus the comparison period.
## Schedule Signals
- Latest run: `2026-03-18T22:09:01.124380+00:00`
- Schedule health score: **50.0**
- Issues total: **570**
- Open starts / finishes: **30 / 101**
- Cycles: **2**
- Top risk flags: none published
## Financial Signals
- Current report month: **2026-03**
- Trust tier: **High**
- Parse status: **success**
- Projected profit: **$1,336,927**
- Margin: **5.9%**
- Forecast final cost: **$22,858,197**
## Top Risks
- **Circular schedule logic**: 2 cycle(s) remain in the latest published schedule output.
- **Open-end exposure**: 30 open starts and 101 open finishes remain.
- **Profit fade**: Projected profit declined by $190,454 from 2026-02.
- **Margin pressure**: Current margin is 5.9%, below the watch threshold.
## Required Actions
- **High / Scheduler**: Validate and remove 2 schedule cycle(s) before the next publish.
- **High / Scheduler**: Validate missing successors and predecessors across 131 open-end activities.
- **Medium / PM / Finance**: Validate margin erosion in the latest ProfitIntel snapshot.
- **Medium / Scheduler**: Validate elevated parser warnings before acting on the current schedule logic.
## Latest Notable Changes
- Top schedule driver is 34992 - Frame Walls & Set Door Frames.
- ProfitIntel selected 2026-03 as the authoritative financial snapshot for 219128 compared against 2026-02. Projected profit decreased to $1,336,927 from $1,527,381. Margin decreased to 5.9% from 6.8%. Forecast final cost increased to $22,858,197 from $22,651,932. Trust tier is high.
- Schedule held flat versus the prior run. Financial posture was effectively unchanged. No material risk movement was detected against the prior run.
## Decision / Risk Rollup
- Immediate escalation needed: **Yes**
- Missing-data flags: schedule_parser_warning_elevated
- Trust rationale:
- ScheduleLab parser warnings are elevated (2284), so schedule traceability needs review.
## Source Provenance
- `schedulelab` | `schedule_dashboard_feed` | `/app/schedulelab_data/published/runs/SU_WAVERLY/outputs/dashboard_feed.json`
- `schedulelab` | `schedule_summary` | `/app/schedulelab_data/published/runs/SU_WAVERLY/outputs/summary.json`
- `schedulelab` | `schedule_run_manifest` | `/app/schedulelab_data/published/runs/SU_WAVERLY/outputs/run_manifest.json`
- `schedulelab` | `schedule_management_actions` | `/app/schedulelab_data/published/runs/SU_WAVERLY/outputs/management_actions.json`
- `schedulelab` | `schedule_management_brief` | `/app/schedulelab_data/published/runs/SU_WAVERLY/outputs/management_brief.md`
- `schedulelab` | `schedule_milestone_drift_log` | `/app/schedulelab_data/published/runs/SU_WAVERLY/outputs/milestone_drift_log.csv`
- `profitintel` | `profitintel_validation_db` | `/app/data/runtime/profitintel.db`
- `profitintel` | `profitintel_workbook` | `/app/data/runtime/production_ingest/20260327T155938-0400/raw_reports/219128/219128 Profit Report Update_2026-03-25.xlsx`