Promoted project 1

Waverly Dorm

SU_WAVERLY

Projected finish 2027-08-16
Movement Vs Prior Trusted Run 0 days

Delta-sensitive comparison is authoritative against 2026-03-28T21-09-05Z.

Primary Issue / Driver Top schedule driver 34992 - Frame Walls & Set Door Frames: high_logic_density; high_successor_count; high_predecessor_count; constrained.

no date movement versus the prior run.

Required Action Scheduler: Validate and remove 2 schedule cycle(s) before the next publish.

Timing: before next publish

Finish Authority trusted comparison

Published milestone drift log

Derived from the published milestone drift log using the latest milestone finish 2027-08-16 (Project Substantial Completion, activity 142).

Trust / Baseline State Authoritative delta-driven ranking
Comparison Detail Trusted prior distinct run selected Delta-sensitive comparison is authoritative against 2026-03-28T21-09-05Z.
Supporting detail below

Arena leads with finish, movement, issue, action, and trust for each promoted project. Expanded narrative, metrics, and evidence follow.

Headline posture Presenter cue

Portfolio requires intervention: 1 project(s) carry HIGH risk and average health is 13.0.

Lead with posture and decision. Expand only if challenged.

What changed SU_WAVERLY

SU_WAVERLY: no date movement versus the prior run.

Projected finish: 2027-08-16.

Why it matters SU_WAVERLY

SU_WAVERLY: 2 cycle(s) remain in the latest published schedule output.

Projected finish: 2027-08-16.

What needs decision SU_WAVERLY

SU_WAVERLY: Scheduler: Validate and remove 2 schedule cycle(s) before the next publish.

before next publish.

What changed Material Changes SU_WAVERLY: no date movement versus the prior run.
SU_WAVERLY Expand

Waverly Dorm

Project: SU_WAVERLY

Finish: Projected finish: 2027-08-16

Delta: Movement vs prior trusted run: 0 days

What changed: no date movement versus the prior run.

Cause: Top schedule driver 34992 - Frame Walls & Set Door Frames: high_logic_density; high_successor_count; high_predecessor_count; constrained.

Impact: Projected finish: 2027-08-16. Movement vs prior trusted run: 0 days. Risk level remains HIGH.

Why it matters: 2 cycle(s) remain in the latest published schedule output.

Action: Scheduler: Validate and remove 2 schedule cycle(s) before the next publish.

Timing: before next publish

Why it matters Why It Matters SU_WAVERLY: no date movement versus the prior run.
SU_WAVERLY Expand

Waverly Dorm

Project: SU_WAVERLY

Finish: Projected finish: 2027-08-16

Delta: Movement vs prior trusted run: 0 days

What changed: no date movement versus the prior run.

Cause: Top schedule driver 34992 - Frame Walls & Set Door Frames: high_logic_density; high_successor_count; high_predecessor_count; constrained.

Impact: Projected finish: 2027-08-16. Movement vs prior trusted run: 0 days. Risk level remains HIGH.

Why it matters: 2 cycle(s) remain in the latest published schedule output.

Action: Scheduler: Validate and remove 2 schedule cycle(s) before the next publish.

Timing: before next publish

What needs decision Required Actions / Decisions SU_WAVERLY: no date movement versus the prior run.
SU_WAVERLY Expand

Waverly Dorm

Project: SU_WAVERLY

Finish: Projected finish: 2027-08-16

Delta: Movement vs prior trusted run: 0 days

What changed: no date movement versus the prior run.

Cause: Top schedule driver 34992 - Frame Walls & Set Door Frames: high_logic_density; high_successor_count; high_predecessor_count; constrained.

Impact: Projected finish: 2027-08-16. Movement vs prior trusted run: 0 days. Risk level remains HIGH.

Why now: 2 cycle(s) remain in the latest published schedule output.

Action: Scheduler: Validate and remove 2 schedule cycle(s) before the next publish.

Timing: before next publish

Rising risks Rising Risks / Watch Items SU_WAVERLY: no date movement versus the prior run.
SU_WAVERLY Expand

Waverly Dorm

Project: SU_WAVERLY

Finish: Projected finish: 2027-08-16

Delta: Movement vs prior trusted run: 0 days

What changed: no date movement versus the prior run.

Cause: Top schedule driver 34992 - Frame Walls & Set Door Frames: high_logic_density; high_successor_count; high_predecessor_count; constrained.

Impact: Projected finish: 2027-08-16. Movement vs prior trusted run: 0 days. Risk level remains HIGH.

Risk signal: 2 cycle(s) remain in the latest published schedule output.

Action: Scheduler: Validate and remove 2 schedule cycle(s) before the next publish.

Timing: before next publish

Professional Portfolio 1. Waverly Dorm no date movement versus the prior run.
Scheduler: Validate and remove 2 schedule cycle(s) before the next publish. SU_WAVERLY
Professional Portfolio

Waverly Dorm

SU_WAVERLY | professional

Speak To This Now

SU_WAVERLY: no date movement versus the prior run.

Finish: Projected finish: 2027-08-16

Delta: Movement vs prior trusted run: 0 days

What changed: no date movement versus the prior run.

Decision / action: Scheduler: Validate and remove 2 schedule cycle(s) before the next publish.

Timing: before next publish

Why It Matters

2 cycle(s) remain in the latest published schedule output.

Cause: Top schedule driver 34992 - Frame Walls & Set Door Frames: high_logic_density; high_successor_count; high_predecessor_count; constrained.

Impact: Projected finish: 2027-08-16. Movement vs prior trusted run: 0 days. Risk level remains HIGH.

Trust / Authority

trusted comparison

Derived from the published milestone drift log using the latest milestone finish 2027-08-16 (Project Substantial Completion, activity 142).

Delta-sensitive comparison is authoritative against 2026-03-28T21-09-05Z.

Key Metrics
Health 13.0
Risk HIGH
Domain Professional
Finish 2027-08-16
Finish Move 0 days
Supporting Evidence
  • Circular schedule logic: 2 cycle(s) remain in the latest published schedule output.
  • Open-end exposure: 30 open starts and 101 open finishes remain.
  • Profit fade: Projected profit declined by $190,454 from 2026-02.
  • Top schedule driver is 34992 - Frame Walls & Set Door Frames.
  • ProfitIntel selected 2026-03 as the authoritative financial snapshot for 219128 compared against 2026-02. Projected profit decreased to $1,336,927 from $1,527,381. Margin decreased to 5.9% from 6.8%. Forecast final cost increased to $22,858,197 from $22,651,932. Trust tier is high.
  • Schedule held flat versus the prior run. Financial posture was effectively unchanged. No material risk movement was detected against the prior run.