Waverly Dorm
Project: SU_WAVERLY
Finish: Projected finish: 2027-08-16
Delta: Movement vs prior trusted run: 0 days
What changed: no date movement versus the prior run.
Cause: Top schedule driver 34992 - Frame Walls & Set Door Frames: high_logic_density; high_successor_count; high_predecessor_count; constrained.
Impact: Projected finish: 2027-08-16. Movement vs prior trusted run: 0 days. Risk level remains HIGH.
Why it matters: 2 cycle(s) remain in the latest published schedule output.
Action: Scheduler: Validate and remove 2 schedule cycle(s) before the next publish.
Timing: before next publish